Inspection & Test Plan (ITP)
Pier / Abutment Shaft Construction Works (RCC Bridge Works)
Legend:
H = Hold Point (Work cannot proceed without approval)
W = Witness Point (Engineer may witness)
R = Review/Record verification
1. Setting Out & Survey Works
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| Verification of centerline & coordinates | Check against approved drawings | GFC Drawings | Contractor / Engineer | H |
| Level & TBM confirmation | Benchmark validation | Survey SOP | Surveyor / Engineer | W |
| Staking of pier/abutment location | Accuracy of layout (tolerance check) | IRC SP-13 | Engineer | H |
2. Excavation / Foundation Works
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| Excavation level & dimensions | As per drawing limits | GFC Drawings | Engineer | H |
| Soil bearing strata verification | Geotechnical confirmation | Geotech Report | Engineer / Geotech | H |
| Blinding concrete | Thickness & level check | Specs | Engineer | W |
3. Reinforcement Work
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| BBS approval | Bar cutting & bending verification | Approved Drawings | Engineer | H |
| Reinforcement placement | Spacing, cover, lap length | IRC:112 | Engineer | W |
| Final cage inspection | Before shuttering closure | GFC Drawings | Engineer | H |
4. Formwork / Shuttering
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| Formwork design approval | Structural stability check | IS 14687 | Engineer | H |
| Erection & alignment | Verticality & leakage control | Method Statement | Engineer | W |
| Final shuttering approval | Pre-pour inspection | QA/QC | Engineer | H |
5. Concreting Works
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| Concrete mix design | Approval of design mix | IRC / MORTH | Engineer | H |
| Slump test | Workability check | IS 1199 | QA/QC | W |
| Cube casting | 7 & 28 day strength test | IS 516 | QA/QC | W |
| Concrete pouring approval | Pre-pour clearance | Method Statement | Engineer | H |
6. Curing & Finishing
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| Curing method | Water/compound curing | Specs | Engineer | W |
| Minimum curing period | 7–14 days compliance | IRC | Engineer | R |
| Surface finishing | Honeycomb inspection | QA/QC | Engineer | W |
7. Final Inspection
| Activity | Inspection Requirement | Reference | Responsibility | Type |
|---|
| Dimensional check | Verticality & alignment | GFC Drawings | Engineer | H |
| Surface inspection | No cracks/honeycombing | QA/QC | Engineer | W |
| As-built documentation | Final record submission | QA System | Contractor | H |
Summary:
Hold Points: Layout approval, foundation approval, reinforcement inspection, shuttering approval, pre-pour clearance, final inspection
Witness Points: Survey checks, reinforcement placement, testing, concreting, curing