Profile Corrective Course (DBM) Construction Methodology
This work involves preparing an existing road surface (granular or bituminous) and laying a bituminous mix, typically 50 mm to 100 mm thick, to correct the pavement profile and strengthen the surface.
1.0 Scope and Preparation
The Profile Corrective Course (PCC) is a layer of varying thickness designed to correct the existing pavement profile (e.g., local depressions, sags, or incorrect camber/super-elevation) before the main overlay.
Existing Bituminous Surface
Repair: Existing potholes and cracks must be repaired and sealed according to relevant specifications (MoRT&H Clauses 3004.2 and 3004.3).
Scarifying: Where specified, the existing bituminous layer is carefully removed without disturbing the underlying layers. The exposed base is reworked, compacted, and primed (Clause 502) if needed.
Tack Coat: After preparation, a Tack Coat (bituminous emulsion) is applied to the surface before laying the new DBM.
Existing Granular Surface
All loose materials are removed, and the surface is prepared to be firm and clean.
If the PCC is bituminous, the granular surface must be primed (Clause 502) after removing loose material.
The surface must be free from dust and capable of being swept by a mechanical broom.
Pre-Laying Checks
Before and after scarifying/preparation, the existing road top levels must be checked and recorded by the Engineer's representative.
2.0 Resource Arrangement: Plant & Equipment
Sl. No.
Name of Equipment
Nos.
1
Batch Type Hot Mix Plant (Capacity 200 TPH)
01
2
Sensor Paver (Automatic Screed Control)
01
3
Pneumatic Tyred Roller (PTR)
01
4
Tandem Vibratory Roller
02
5
Bitumen Sprayer (for Tack Coat)
01
6
Compressor / Hydraulic Broom
01
7
Water Tanker
01
8
Tipping Trucks
As Required
3.0 Materials and Mix Production
3.1 Materials
Aggregates: Coarse and fine aggregates from approved quarries.
Bitumen: VG-30 or VG-40 grade from approved sources.
Tack Coat: Rapid setting Bituminous Emulsion from approved sources.
3.2 Job Mix Formula (JMF)
The JMF determines the precise proportions of coarse aggregates, fine aggregates, bitumen, and mineral filler/additives. It is designed in the site laboratory and must be approved by the Independent Engineer (AE/IE)/PMC. The process is the same as we do for DBM & BC mix designs.
3.3 Hot Mix Plant Operation
Storage: Bitumen (VG-30/VG-40) stored in automatic temperature-controlled tanks (150°C to 165°C).
Aggregates: Separate cold bins and feeders proportion the aggregates and dust into the dryer.
Drying: Dryer continuously heats and dries aggregates (150°C to 170°C) minimizing fuel consumption and dust release.
Mixing: Aggregates and binder combined in an inert, steam-laden atmosphere. Bitumen Temp: 150°C–165°C, Aggregate Temp: 150°C–170°C, Mixture Max Temp: 165°C.
4.0 Laying and Compaction
4.1 Transportation of Mix
Mix loaded into tipping trucks (up to 20 MT). Beds sprayed with release agent. Covered with tarpaulin to maintain temperature.
Temperature at loading: 155°C to 165°C.
4.2 Application of Tack Coat
Applied using a mechanical sprayer. Rate: 0.25–0.30 Kg/m². Emulsion Temp: 20°C–70°C.
Allow tack coat to cure before DBM layer is laid.
4.3 Spreading and Finishing
Sensor wire fixed over brackets at 10m intervals. Paver guided to achieve designed finished levels.
Laying temperature (Min): 125°C. Paver uses fully activated screed with tampers/vibrators. Loose thickness allowance: 25%. Manual methods for irregular areas.
4.4 Compaction
Equipment: Vibratory Tandem Roller + PTR.
Rolling sequence: From lower end to higher side. Passes determined on-site.
Density: Rolling until specified density achieved or no further movement. Transverse joints cut full thickness; edges painted with hot bitumen/tack coat.
5.0 Quality Control and Traffic
Core Cutting: After 24 hours to check density.
Bitumen Testing: Softening Point, Penetration, Ductility for each consignment.
Surface Finish: Must conform to Clause 902 of MoRT&H.
Opening to Traffic: Minimum 24 hours after laying. Traffic diversion with cones, caution boards, flagmen.
Top FAQs – DBM Profile Corrective Course
What is PCC? A layer to correct existing pavement profile before overlay.
When is it required? For depressions, potholes, uneven camber or sags.
Typical thickness? 50–100 mm per layer.
Materials used? Aggregates, VG-30/VG-40 bitumen, mineral filler, tack coat.
Surface preparation? Scarify, repair cracks/potholes, broom sweep, prime or tack coat.
Compaction method? PTR + Tandem Vibratory Rollers until specified density.
Joints? Full-depth transverse cut, edges coated with hot bitumen/tack coat.