Table of Contents
Toggle
Author: Kishor Kumar | Category: Bituminous Works | As per MoRTH Clause 507
The Dense Bituminous Macadam (DBM) layer forms the primary structural course in flexible pavement construction. It provides load distribution, structural strength, and surface uniformity before the Bituminous Concrete (BC) wearing course is laid.
This field-ready guide covers MoRTH specifications, asphalt plant requirements, mix design parameters, layer thickness criteria, temperature control, compaction standards, and complete QA/QC procedures—making it practical for site engineers, QA/QC professionals, and highway contractors.
Most premature pavement failures—such as rutting, fatigue cracking, shoving, and delamination—originate from poor DBM execution. Incorrect binder content, inadequate compaction, segregation during laying, improper joint construction, or temperature loss during transportation and paving can significantly reduce pavement service life.Since DBM acts as the structural backbone of flexible pavements, strict compliance with MoRTH specifications, proper mix design control, and systematic field quality checks are essential to ensure long-term pavement performance.
Job Mix Design for DBM shall be conducted in the Field Laboratory using Marshall Method. The materials shall be collected directly from the stockyard / storage tank and shall be checked for various physical requirements.
The testing shall be carried out in the presence of the Consultant and submitted for approval.
Approval of JMF: Approval shall be based on witnessed testing by the Independent Engineer. Samples shall be tested in in-house QC lab. Any change in material source requires submission of new JMF for approval prior to execution.
Once the plant trials have been successfully completed and approved, the laying trials are executed to demonstrate that the proposed mix can be successfully laid and compacted in accordance with Clause 501. The laying trial shall be carried out on a suitable area which is not to form part of the works. The area of the laying trials shall be a minimum of 100 sq. m. of construction similar to that of the project road, and it shall be in all respects, particularly compaction, the same as the project construction, on which the bituminous material is to be laid.
Information to AE is given of the proposed method for laying and compacting the material. The density of the finished paving layer shall be determined by taking cores, no sooner than 24 hours after laying. Once the laying trials have been approved, the same plant and methodology shall be applied to the laying of the material on the project.
Tack Coat shall consist of the application of a single coat of low viscosity liquid bituminous material on the existing bituminous surface using a calibrated boom pressure sprayer, ensuring uniform and continuous coverage. The application shall be carried out at a controlled speed of approximately 45 km/hour to achieve proper bonding between existing surface and subsequent bituminous layers.
Hot Mix shall be transported in rear tipping dumpers of minimum 10T capacity or higher, ensuring uninterrupted supply to the paver. All vehicles shall be clean, leak-proof, and properly insulated where required.
To prevent heat loss, each dumper shall be fully covered with heavy-duty tarpaulin immediately after loading. The mix temperature shall be monitored at plant, dispatch, and site to ensure compliance with MoRTH specifications.
Paving shall be carried out using a high-performance Asphalt Paver equipped with hydraulically extendable screed capable of maintaining precise longitudinal and transverse profiles, gradients, and levels.
Pavers of approved make shall be deployed, capable of paving up to 11.0 m width for full carriageway laying. For service roads and restricted areas, pavers capable of paving up to 5.5 m width shall be used.
Continuous and uniform paving shall be ensured without segregation, with automatic sensor control wherever applicable to maintain specified thickness and smooth riding quality.
The temperature of the mix at the time of laying shall be strictly maintained as per approved Job Mix Formula (JMF). Any material outside permissible temperature limits shall be rejected at site.
| Bitumen Grade | Bitumen Temp (°C) | Aggregate Temp (°C) | Mixing Temp (°C) | Laying Temp (°C) | Rolling Temp (Start ≥ °C) |
|---|---|---|---|---|---|
| VG-40 | 160 - 170 | 160 - 175 | 160 - 170 | 150 - 165 | 150 Min |
| VG-30 | 150 - 165 | 160 - 175 | 150 - 165 | 145 - 165 | 140 Min |
| VG-20 | 145 - 165 | 150 - 165 | 145 - 165 | 140 - 160 | 135 Min |
| VG-10 | 140 - 160 | 150 - 165 | 140 - 160 | 130 - 150 | 130 Min |
Note: Rolling must be completed before the mat cools down to the specified minimum rolling temperatures to ensure proper compaction and interlocking of aggregates.
Breakdown rolling shall commence immediately behind the paver and shall start only when the mix temperature is below 120°C and stable enough to avoid displacement or cracking.
Rolling shall be completed before the mix temperature falls below 80°C to ensure optimum density and interlocking of aggregates.
Compaction shall be achieved using a combination of:
Final rolling shall ensure elimination of roller marks and achievement of uniform density across the entire surface width.
Finished surface levels shall be jointly verified with the Consultant and compared with approved design levels and tolerances.
Field density shall be checked using Sand Replacement Method or Nuclear Density Gauge at specified frequency as per QA/QC plan.
Core samples shall be extracted using a calibrated core cutting machine. All laboratory tests including thickness, density, and bitumen content shall be carried out to ensure compliance with approved specifications and JMF.
The newly laid bituminous surface shall be opened to traffic only after complete cooling to ambient temperature or after a minimum curing period of 24 hours, whichever is later, and subject to approval of the Engineer.
| Grading | 1 | 2 |
|---|---|---|
| Nominal aggregate size | 37.5 mm | 26.5 mm |
| Layer Thickness | 75-100 mm | 50-75 mm |
| 45.00 | 100 | - |
| 37.50 | 95-100 | 100 |
| 26.50 | 63-93 | 90-100 |
| 19.00 | - | 71-95 |
| 13.20 | 55-75 | 56-80 |
| 9.5 | - | - |
| 4.75 | 38-54 | 38-54 |
| 2.36 | 28-42 | 28-42 |
| 1.18 | - | - |
| 0.600 | - | - |
| 0.300 | 7-21 | 7-21 |
| 0.150 | - | - |
| 0.075 | 2-8 | 2-8 |
| Bitumen Content | Min 4.0% | Min 4.5% |
| Layer | Inspection Stage | Test / Parameter | Standard | Frequency | Acceptance Criteria | |||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Dense Bituminous Macadam (DBM) | Inspection at Source – Properties of Binder & Aggregate | Quality of Binder | IS:1201 to IS:1220 & IS:15462 | 1 Sample / Lot |
Ordinary Bitumen complying with IS:73 (2013) Modified Bitumen complying with IRC:SP:53 (2010) | |||||||||||||||||||||||||||||
| Aggregate Impact Value | IS:2386 (Part 4) | 1 Test / 350 m³ | 27% (Max) | |||||||||||||||||||||||||||||||
| Los Angeles Abrasion Value | IS:2386 (Part 4) | As & when Required | 35% (Max) | |||||||||||||||||||||||||||||||
| Combined Flakiness & Elongation Index | IS:2386 (Part 1) | 1 Test / 350 m³ | 35% (Max) | |||||||||||||||||||||||||||||||
| Stripping Value | IS:6241 | 1 Test / Source | Minimum retained coating 95% | |||||||||||||||||||||||||||||||
| Soundness Test | IS:2386 (Part 5) | 1 Test / Source |
12% max with Sodium Sulphate 18% max with Magnesium Sulphate | |||||||||||||||||||||||||||||||
| Water Absorption Value | IS:2386 (Part 3) | 1 Test / Source | 2% (Max) | |||||||||||||||||||||||||||||||
| Sand Equivalent Value | IS:2720 (Part 37) | 1 Test / Source | 50% (Min) | |||||||||||||||||||||||||||||||
| % Age of Fractured Face | IS:2386 (Part 1) | As & when Required | 90% of material retained on 4.75 mm sieve shall have at least 2 fractured faces | |||||||||||||||||||||||||||||||
| Plasticity Index | IS:2720 (Part 5) | 1 Test / Source | 4% (Max) | |||||||||||||||||||||||||||||||
| Inspection at Source – Properties of Mix | Aggregate Grading (Mix Aggregates) | IS:2386 (Part 1) |
1 Test / 400 MT of Mix Minimum 2 Tests / Plant / Day |
MoRTH Spec (5th Rev.) Table 500-10 | ||||||||||||||||||||||||||||||
| Marshall Stability | ASTM D-1559 / AASHTO T245 |
Set of 3 Specimens / 400 MT of Mix Minimum 2 Sets / Plant / Day | As per Table 500-10 of MoRTH Specification | |||||||||||||||||||||||||||||||
| Marshall Flow | ASTM D-1559 / AASHTO T245 |
Set of 3 Specimens / 400 MT of Mix Minimum 2 Sets / Plant / Day | As per Table 500-10 of MoRTH Specification | |||||||||||||||||||||||||||||||
| Air Voids | ASTM D-2726 |
Set of 3 Specimens / 400 MT of Mix Minimum 2 Sets / Plant / Day | As per Table 500-10 of MoRTH Specification | |||||||||||||||||||||||||||||||
| Voids in Mineral Aggregate (VMA) | ASTM D-2726 |
Set of 3 Specimens / 400 MT of Mix Minimum 2 Sets / Plant / Day | As per Table 500-10 of MoRTH Specification | |||||||||||||||||||||||||||||||
| Voids Filled by Bitumen (VFB) | ASTM D-1559 |
Set of 3 Specimens / 400 MT of Mix Minimum 2 Sets / Plant / Day | As per Table 500-10 of MoRTH Specification | |||||||||||||||||||||||||||||||
| Binder Content | ASTM D-2172 |
1 Test / 400 MT of Mix Minimum 2 Tests / Plant / Day |
4% (Min) for Grade-I 4.5% (Min) for Grade-II | |||||||||||||||||||||||||||||||
| Maximum Specific Gravity of Mix (Gmm) | ASTM D-2041 |
1 Test / 400 MT of Mix Minimum 2 Tests / Plant / Day | As per Approved Mix Design | |||||||||||||||||||||||||||||||
|
Water Sensitivity Test (if retained coating in stripping test is less than 95%) | AASHTO T283 | 1 Test / Mix (When Source of Material Changes) | 80% (Min) | |||||||||||||||||||||||||||||||
| Control of Temperature | Control of Temperature of Binder in Boiler & Aggregate in Dryer | MoRTH Specifications | Every Day Prior to Production Starts |
Aggregate Temp: 150°C–170°C Binder Temp: 150°C–165°C Discharge Temp: 150°C–165°C Modified Bitumen: Aggregate Temp: 150°C–185°C Binder Temp: 165°C–185°C Discharge Temp: 150°C–170°C | ||||||||||||||||||||||||||||||
| Permissible Variations of Plant Mix from Job Mix Formula | Aggregate Grading | MoRTH Specifications | NA |
|
| Category | Item | Reference / Standard | Frequency | Requirement / Criteria |
|---|---|---|---|---|
| In-process Inspection | Check level control of paver | MORTH Specifications | At regular close intervals | - |
| Temperature of mix before laying and rolling | MORTH Specifications | At regular close intervals |
Laying Temp. 140°C (Min) Rolling Temp. 90°C (Min) | |
| Acceptance Criteria | Control of Compaction (Field Density) | ASTM-D 2726 | 1 Test / 700 m² | As per MORTH Cl 903.4.2 |
| Tolerance in Surface Level | Standard survey practice | As per Specification | +6 mm or -6 mm | |
| Surface Regularity | IRC-SP-16 | As & when Required | Bituminous Base Course 6 mm | |
| Binder Tolerance | ± 0.3% | |||
| Mixing Temperature Tolerance | ± 10°C | |||
DBM must achieve at least 98% of Marshall Density as per MoRTH.
No. DBM shall not be laid during rain or on wet surfaces.
DBM acts as a binder/base course, while BC is the wearing course with finer gradation.
Standard construction methodologies for highway works as per MoRTH 5th Revision and IRC Specifications.