Table of Contents

Top 9 Proven Steps for Bituminous Concrete (BC) | MoRTH Clause 507

Top 9 Proven Steps for Bituminous Concrete (BC) Construction

Quick Summary:
Bituminous Concrete (BC) is the final wearing course of flexible pavement laid in 30–50 mm thickness over DBM or bituminous base. Construction shall strictly follow MoRTH Clause 507, including approved mix design, controlled laying temperature, proper compaction and quality control tests.

1. Scope

Methodology for laying of DBM in this project is detailed herein under. This method statement is based on parameters conforming to MoRTH, MS-2 Specifications. The construction of pavement layers on existing road involves the dismantling of existing bituminous layers, widening and strengthening of the existing road. This work covers preparation of surface, tack coat application, production of BC mix, transportation, laying, compaction, joint treatment and quality control testing in accordance with MoRTH Clause 507.

2. Reference Standards

  • MoRTH Specifications – Clause 507 (5th Revision)
  • IRC: SP: 84 – Manual of Specifications
  • IS: 73 & IS: 15462 – Bitumen Standards
  • IS: 2386 (All Parts) – Aggregate Testing Standards
  • ASTM / AASHTO and MS-2 7th Rev– Marshall Mix Design
  • Top Level Sheet – DBM (Dense Bituminous Macadam): Approved Mix Design & Approved GFC Drawings

3. Equipment Required

  • Hot Mix Plant with automatic controls
  • Self-propelled sensor paver with electronic, tamping/vibrating extendible screed (as per Clause 501.5)
  • Tandem vibratory rollers
  • Pneumatic Tyred Roller (PTR), 12–15 tonnes with minimum tyre pressure of 5.6 kg/cm²
  • Bitumen pressure distributor/sprayer with accessories (as per Clause 502.4.1)
  • Mechanical broom and air compressor for surface cleaning
  • Core cutting machine for density testing
  • Sufficient number of tippers for continuous and uninterrupted laying

Materials & Job Mix Design

    Test Procedure of DBM & BC Mix Design (as per MoRTH & IRC Specifications)

    1. 1: Raise RFI for sampling of aggregates for DBM/BC mix design.
    2. 2: Sample the cold bin individual aggregates jointly.
    3. 3: Conduct individual gradation for aggregate as mentioned in MoRTH 500-10.
    4. 4: Blend the aggregate to meet the specified limits as mentioned in MoRTH 500-10.
    5. 5: Conduct the tests for aggregate to confirm its suitability for asphalt mix works:
    6. 6: AIV or LAAV, FI & EI, Stripping value, Water Absorption, Sand Equivalent value test to meet its suitability for DBM & BC as mentioned in MoRTH.
    7. 7: Feed the cold bin blending aggregate proportion in the Hot Mix Plant & take the individual hot bin aggregates.
    8. 8: Conduct specific gravity & water absorption test in the hot bin aggregates.
    9. Sl. No. 9: Conduct the individual gradation for aggregate & blend the aggregate to achieve the limit specified in MoRTH Table 500-10.
    10. 10: Feed the obtained blending proportion in the Hot Mix Plant and take the combined mix sample and check the combined gradation tests as mentioned in MoRTH 500-10.
    11. 11: Conduct the following tests for bitumen: Softening Point Test, Penetration Test, Viscosity Test from the approved bitumen source.
    12. 12: Prepare the mix with different binder content & find the Maximum Specific Gravity of the mix as per ASTM D-2041.
    13. 13: Cast the Marshall moulds with different binder content to check VMA, VFB, GSA, Air Voids, Stability & Flow of the mix.
    14. 14: With the obtained result plot the graph for Bulk Density, Marshall Stability, Air Voids, Flow, VMA & VFB.
    15. 15: All test data are interpreted & marked at which % all criteria passes.
    16. 16: Optimum Binder Content (OBC) has been found from chart.
    17. 17: Retained Stability Test conducted at OBC.
    18. 18: Refusal Density of the BC mix to be checked at 75, 150, 300 blows.
    19. 19: Marshall Quotient found for BC as per Table 7 of IRC SP:53-2002.
    20. 20: Confirmatory moulds casted & tested for Stability, Flow, VFB, VMA.
  • Bituminous material of VG-40 grade shall confirm to the specifications of IS-73(2013). If modified binder is used then CRMB / PMB conforming to the requirement of CL.501.2.1, 507.2.1, IRC-SP-53-2010 and IS 15462-2004. Approved Aggregate and filler shall confirm two of MoRTH Cl.501.2 & Cl.507.2.
  • Job Mix Formula (JMF): The Job Mix Formula (JMF) for Bituminous Concrete (BC) shall be developed and approved for use in the works in the presence of the Authority Engineer. The JMF shall include the following details:
    • Source and location of all materials (bitumen, coarse aggregate, fine aggregate, and filler)
    • Proportions of all constituent materials
    • Binder type and percentage by weight of total mixture
    • Coarse aggregate, fine aggregate, and mineral filler percentage
    • Combined grading with specified sieve passing limits as per BC requirements
    • Marshall test results as per Table 500-11 (Stability, Flow, Density, Air Voids, VMA, VFB)
    • Aggregate compliance with MoRTH Clause 501.2 & Clause 507.2
    • Mixing, laying, and compaction temperature ranges
    • Optimum Bitumen Content (OBC) and volumetric properties of mix
  • Job Mix Design for BC shall be conducted in the Field Laboratory using Marshall Method. The materials shall be collected directly from the stockyard / storage tank and shall be checked for various physical requirements.

    The testing shall be carried out in the presence of the Consultant and submitted for approval.

    Approval of JMF: Approval shall be based on witnessed testing by the Independent Engineer. Samples shall be tested in in-house QC lab. Any change in material source requires submission of new JMF for approval prior to execution.

  • Plant Trials: After laboratory approval, plant trials shall be conducted to ensure uniform mix production. Permissible variations shall comply with Table 500-13 limits.
  • Laying Trials:

    Once the plant trials have been successfully completed and approved, the laying trials are executed to demonstrate that the proposed mix can be successfully laid and compacted in accordance with Clause 501. The laying trial shall be carried out on a suitable area which is not to form part of the works. The area of the laying trials shall be a minimum of 100 sq. m. of construction similar to that of the project road, and it shall be in all respects, particularly compaction, the same as the project construction, on which the bituminous material is to be laid.

    Information to AE is given of the proposed method for laying and compacting the material. The density of the finished paving layer shall be determined by taking cores, no sooner than 24 hours after laying. Once the laying trials have been approved, the same plant and methodology shall be applied to the laying of the material on the project.

    Tack Coat shall consist of the application of a single coat of low viscosity liquid bituminous material on the existing bituminous surface using a calibrated boom pressure sprayer, ensuring uniform and continuous coverage. The application shall be carried out at a controlled speed of approximately 45 km/hour to achieve proper bonding between existing surface and subsequent bituminous layers.

Transportation, Paving & Compaction Methodology (Enhanced)

1. Transportation of Bituminous Mix

Hot Mix shall be transported in rear tipping dumpers of minimum 10T capacity or higher, ensuring uninterrupted supply to the paver. All vehicles shall be clean, leak-proof, and properly insulated where required.

To prevent heat loss, each dumper shall be fully covered with heavy-duty tarpaulin immediately after loading. The mix temperature shall be monitored at plant, dispatch, and site to ensure compliance with MoRTH specifications.

2. Paving Operations

Paving shall be carried out using a high-performance Asphalt Paver equipped with hydraulically extendable screed capable of maintaining precise longitudinal and transverse profiles, gradients, and levels.

Pavers of approved make shall be deployed, capable of paving up to 11.0 m width for full carriageway laying. For service roads and restricted areas, pavers capable of paving up to 5.5 m width shall be used.

Continuous and uniform paving shall be ensured without segregation, with automatic sensor control wherever applicable to maintain specified thickness and smooth riding quality.

3. Temperature Control

The temperature of the mix at the time of laying shall be strictly maintained as per approved Job Mix Formula (JMF). Any material outside permissible temperature limits shall be rejected at site.

🔥 Concrete Pack ₹299
Buy Now

Table 500-2: Mixing, Laying and Rolling Temperatures for Bituminous Mixes (°C)

Bitumen GradeBitumen Temp (°C)Aggregate Temp (°C)Mixing Temp (°C)Laying Temp (°C)Rolling Temp (Start ≥ °C)
VG-40160 - 170160 - 175160 - 170150 - 165150 Min
VG-30150 - 165160 - 175150 - 165145 - 165140 Min
VG-20145 - 165150 - 165145 - 165140 - 160135 Min
VG-10140 - 160150 - 165140 - 160130 - 150130 Min

Note: Rolling must be completed before the mat cools down to the specified minimum rolling temperatures to ensure proper compaction and interlocking of aggregates.

4. Rolling & Compaction Sequence

Breakdown rolling shall commence immediately behind the paver and shall start only when the mix temperature is below 120°C and stable enough to avoid displacement or cracking.

Rolling shall be completed before the mix temperature falls below 80°C to ensure optimum density and interlocking of aggregates.

Compaction shall be achieved using a combination of:

  • 10T Double Drum Vibratory Roller (Primary Compaction)
  • Pneumatic Tyre Roller (Secondary Compaction / Kneading Effect)

Final rolling shall ensure elimination of roller marks and achievement of uniform density across the entire surface width.

5. Quality Control & Testing

Finished surface levels shall be jointly verified with the Consultant and compared with approved design levels and tolerances.

Field density shall be checked using Sand Replacement Method or Nuclear Density Gauge at specified frequency as per QA/QC plan.

Core samples shall be extracted using a calibrated core cutting machine. All laboratory tests including thickness, density, and bitumen content shall be carried out to ensure compliance with approved specifications and JMF.

6. Opening to Traffic

The newly laid bituminous surface shall be opened to traffic only after complete cooling to ambient temperature or after a minimum curing period of 24 hours, whichever is later, and subject to approval of the Engineer.

7. Safety & Environmental Management

  • Caution boards shall be installed at entry, exit, and all hazardous locations of work zone.
  • Continuous barricading with reflective tape shall be provided along active work areas.
  • Trained flagmen / signalmen shall be deployed at high traffic density locations.
  • Reflective signage and blinking lights shall be provided during night operations.
  • Hot mix plant shall be operated with valid pollution control measures in place.
  • Noise control and emission control devices shall be maintained in working condition.
  • Construction waste shall be disposed of in designated approved locations only.
  • All necessary precautions shall be taken to avoid public inconvenience and environmental impact.

8. Contractor’s Technical Remarks

  • Manpower and machinery deployment is indicative and may be adjusted based on site requirements and progress.
  • Any modification in execution methodology shall be implemented only after prior approval from the Consultant/Engineer.
  • Full compliance with MoRTH, IRC, and project-specific specifications shall be ensured at all stages of execution.

Additional Items

  1. Spreading in restricted areas shall be done manually.
  2. Hot joints shall be executed before earlier material cools to 100°C. No laying in standing water.
  3. During rain, laying shall stop when water accumulates; rollers may continue compaction.
  4. All tippers shall be covered with tarpaulin during rain.

Daily Progress Reports

  • Date of operation with RFIs
  • Material quantity records
  • Laydown records (location, layer, time, temperature)
  • Plant and labour deployment
  • Laboratory and field test records

Composition of Bituminous Concrete (BC)

Grading12
Nominal Aggregate Size19.0 mm13.2 mm
Layer Thickness50 mm30-40 mm
19.00 mm90-100100
13.20 mm59-7990-100
9.5 mm52-7270-88
4.75 mm35-5553-71
2.36 mm28-4442-58
0.075 mm2-84-10
Bitumen ContentMin 5.2%Min 5.4%

Quality Control Inspection & Frequency

Bituminous Concrete (BC) Quality Control Inspection

Quality Control Inspection & Frequency – Bituminous Concrete (BC)

WorkInspection TypeProperty / TestSpecificationFrequencyRequirement / Criteria
Bituminous Concrete (BC) Inspection at Source – Properties of Binder & AggregateQuality of Binder IS:1201 to IS:1220 & IS:15462 1 Sample / Lot Ordinary Bitumen complying with IS:73 (2013) & Modified Bitumen complying with IRC:SP:53-2010
Aggregate Impact ValueIS:2386 (Part 4)1 Test / 350 m³24% (Max)
Los Angeles Abrasion ValueIS:2386 (Part 4)As & When Required30% (Max)
Combined Flakiness & Elongation IndexIS:2386 (Part 1)1 Test / 350 m³35% (Max)
Sand Equivalent ValueIS:2386 (Part 4)1 Test / Source50% (Min)
Stripping ValueIS:62411 Test / SourceMin Retained Coating 95%
Soundness TestIS:2386 (Part 5)1 Test / Source 12% Max with Sodium Sulphate
18% Max with Magnesium Sulphate
Water Absorption ValueIS:2386 (Part 3)1 Test / Source2% (Max)
Plasticity IndexIS:2720 (Part 5)1 Test / Source4% (Max)
Stone Polishing ValueBS:812-1141 Test / Source55 (Min)
Inspection at Source – Properties of Mix Aggregate Grading (Mix Aggregates) IS:2386 (Part 1) 1 Test / 400 MT of Mix
Minimum 2 Tests / Plant / Day
MoRTH Specification (5th Revision) – Table 500-17
IS Sieve% Passing
Grading-IGrading-II
26.5 mm100-
19 mm90–100100
13.2 mm59–7990–100
9.5 mm52–7270–88
4.75 mm35–5553–71
2.36 mm28–4442–58
1.18 mm20–3434–48
600 Micron15–2726–38
300 Micron10–2018–28
150 Micron5–1312–20
75 Micron2–84–10

Quality Control Tests for Bituminous Mix

TestStandardFrequencyRequirement
Marshall StabilityASTM D1559 / AASHTO T2453 Samples / 400 MT (Min 2 Sets/Day)As per MoRTH
Marshall FlowASTM D1559 / AASHTO T2453 Samples / 400 MT (Min 2 Sets/Day)As per MoRTH
Air VoidsASTM D27263 Samples / 400 MT (Min 2 Sets/Day)As per MoRTH
Voids in Mineral Aggregate (VMA)ASTM D27263 Samples / 400 MT (Min 2 Sets/Day)As per MoRTH
Voids Filled with Bitumen (VFB)ASTM D15593 Samples / 400 MT (Min 2 Sets/Day)As per MoRTH
Binder ContentASTM D21721 Test / 400 MT (Min 2/Day)5.2% (Gr-II), 5.4% (Gr-I)
Water Sensitivity TestAASHTO T2831 Test / MixMinimum 80%

Temperature Control

ParameterTemperature Range
Aggregate Temperature150°C – 170°C
Binder Temperature150°C – 165°C
Discharge Temperature150°C – 165°C

Aggregate Grading – Permissible Variation

Sieve SizePermissible Variation
19 mm & Above±7%
13.2 – 9.5 mm±6%
4.75 mm±5%
2.36 – 1.18 – 0.600 mm±4%
0.300 – 0.150 mm±3%
0.075 mm±1.5%

Other Permissible Variations

ParameterVariation
Binder Content±0.3%
Mixing Temperature±10°C

In-Process Inspection

ActivitySpecificationFrequencyRequirement
Check Level Control of Paver-At Regular Close Intervals-
Temperature of Mix Before Laying & RollingMoRTH SpecificationAt Regular Close Intervals Laying Temperature: 140°C (Min)
Rolling Temperature: 90°C (Min)

Modified Binder:
Laying: 130°C – 160°C
Rolling: 115°C – 155°C

Acceptance Criteria

Test / ParameterStandardFrequencyRequirement
Control of Compaction (Field Density)-(Core Cutting)-NDGASTM D27261 Test / 700 m²As per MORTH Clause 903.4.2
Tolerance in Surface LevelStandard Survey PracticeAs per SpecificationMachine Laid ±6 mm
Surface RegularityIRC-SP-16As & when required3 mm
Roughness (Longitudinal)IRC-SP-16As & when required< 2000 mm/km
Engineer Tip:
Maintaining proper temperature (160–170°C), continuous paving, and correct rolling sequence are the top 3 factors controlling BC quality on site.

Inspection Plan

S.NoActivityInspectionTestsRemarks
1Approval of DBM TopYesYesDensity & levels jointly recorded
2Spreading LayersYes-Method control
3Final LayerYesYesJoint survey
4Density CheckYesYesAfter compaction
  • All transverse and longitudinal joints shall be cut vertically using mechanical cutter to obtain a clean, straight edge and coated with bitumen emulsion before laying adjacent mix.
  • Safety Measures

    • All safety measures shall be as per approved EHS Plan.

    9. Opening to Traffic

    Traffic shall be permitted only after cooling of BC surface and written approval from Engineer-in-Charge.

    Previous Layer → DBM Construction

    🏗️ Highway Construction Methodology Hub

    Standard construction methodologies for highway works as per MoRTH 5th Revision and IRC Specifications.

    🔥 Concrete Pack ₹299
    Buy Now

    Scroll to Top