Top 8 Proven Steps for Dense Bituminous Macadam (DBM) Construction Methodology — MoRTH Clause 507
Top 8 Proven Steps for Dense Bituminous Macadam (DBM) Construction Methodology — MoRTH Clause 507
Author: Kishor Kumar | Category: Bituminous Works | Updated: 2025
Quick Summary: Dense Bituminous Macadam (DBM) is a dense-graded hot mix used as a binder/base course. This article summarises the material requirements, mix design criteria, MoRTH Tables (500-9 to 500-13), and the Top 8 Proven Steps for execution and quality control as per MoRTH Clause 507.
Nominal Sizes: 37.5 mm (Grading 1) / 26.5 mm (Grading 2)
Compacted Thickness: 50–100 mm (single layer) or as per design
Bitumen: VG-30 / VG-40 or PMB as per Contract
Min. Binder Content: Table 500-10 (Min 4.0% for Grading 1; Min 4.5% for Grading 2)
Field Density: ≥ 98% Marshall density (or ≥92% Gmm as per contract)
Scope
This DBM construction methodology provides details of mandatory requirements for construction in single or multiple layers of Dense Bituminous Macadam (DBM) on a previously prepared Wet Mix Macadam base. The thickness of a single layer shall be between 50 mm to 100 mm or as per approved design and drawings.
Codal Provisions
Contract Agreement
IRC: SP: 84-2014
MoRTH Specifications for Road & Bridge Works (5th Revision)
Relevant Drawings
Plant & Equipment Required
The following major plants and machinery shall be deployed for the construction of bituminous works to ensure uniform quality and efficient execution:
Stone Crusher: For producing well-graded aggregates as per MoRTH specifications.
Hot Mix Plant (Batch Type – Recommended): For precise proportioning and uniform mixing of aggregates and bitumen.
Batching Plant & Trial Setup: To ensure calibration and verification of mix proportions before regular production.
Sensor Paver with String Line Arrangement: For achieving required layer thickness, line, and level accuracy.
Steel Tandem and Pneumatic Rollers: For effective compaction and attainment of desired density.
Bitumen Sprayer: For uniform application of tack coat or prime coat.
Dumpers, Air Compressor, and Mechanical Broom: For material transport, cleaning of surfaces, and general site operations.
Additional instruments: Thermometers (0–250°C) for temperature monitoring, thickness gauges for layer measurement, a survey kit for level and alignment checks, and a core cutting machine equipped with 100 mm and 150 mm diameter bits for sampling and density verification.
Requirement of Materials
Material
Requirement / Specification
Bitumen
VG-30 or VG-40 (or PMB as per CA / IS 73 / IS 15462). Grade as per contract / climatic requirements.
Coarse Aggregates
Crushed rock / crushed gravel retained on 2.36 mm; clean, durable, cubical; satisfy LA abrasion/AIV, flakiness & elongation limits.
Fine Aggregates
Passing 2.36 mm, retained on 75 µ; sand equivalent ≥ 50; PI ≤ 4.
Filler
Rock dust / hydrated lime / cement approved by AE; grading per Table 500-9.
Note: Submit material source & test reports for AE approval prior to use.
Table 500-9: Grading Requirements for Mineral Filler
IS Sieve (mm)
Cumulative % Passing
0.6
100
0.3
95–100
0.075
85–100
In bituminous mixes, filler refers to fine material (passing 0.075 mm sieve) added to fill the voids in the mineral aggregate and improve the stability, density, and binding of the mix.
Common Fillers Used in Bituminous Mixes
Ordinary Portland Cement (OPC)
Lime (Hydrated or Quicklime)
Stone Dust / Crusher Dust
Fly Ash
Baghouse Dust
Rock Dust / Mineral Filler
Specification Reference: As per MoRTH Clause 507.2.4 & IS: 73.
Table 500-10: Composition of Dense Graded Bituminous Macadam
Grading
1 (Nominal 37.5 mm)
2 (Nominal 26.5 mm)
Layer thickness (mm)
75–100
50–75
IS sieve 45 mm
100
100
IS sieve 37.5 mm
95–100
100
IS sieve 26.5 mm
63–93
90–100
IS sieve 19 mm
-
71–95
IS sieve 13.2 mm
55–75
56–80
IS sieve 4.75 mm
38–54
38–54
IS sieve 2.36 mm
28–42
28–42
IS sieve 0.3 mm
7–21
7–21
IS sieve 0.075 mm
2–8
2–8
Bitumen content (% by mass)
Min 4.0*
Min 4.5*
The bitumen content is based on aggregates with a specific gravity of 2.7. Adjust for aggregate specific gravity and climatic conditions as required by MoRTH.
Comparison of Standard and Modified Marshall Methods
Parameter
Standard Marshall Test
Modified Marshall Test (ASTM D5581 / MS-2)
Applicable Aggregate Size
Up to 26.5 mm
Up to 38 mm (1.5 inch)
Specimen Diameter
101.6 mm (4 inch)
152.4 mm (6 inch)
Specimen Height
63.5 ± 1.3 mm
95.2 ± 1.3 mm
Hammer Weight
4.5 kg
10.2 kg (mechanical only)
No. of Blows per Face
50 or 75 blows
1.5× standard (75 or 112 blows)
Minimum Stability Criteria
As per MoRTH Table 500-12
2.25 × standard value
Flow Value
2–4 mm
3–6 mm (1.5× range)
The Modified Marshall Method is adopted for bituminous mixes containing aggregates up to 38 mm nominal size (such as DBM Grading 1).
Table 500-13: Permissible JMF Variations
Parameter
Permissible Variation
Aggregate passing 19 mm or larger
±8%
Aggregate passing 13.2 / 9.5 mm
±7%
Aggregate passing 4.75 mm
±6%
Aggregate passing 2.36 / 1.18 / 0.6 mm
±5%
Aggregate passing 0.3 / 0.15 mm
±4%
Aggregate passing 0.075 mm
±2%
Binder content
±0.3%
Mixing temperature
±10°C
MoRTH allows tolerances in production to ensure performance — see Table 500-13 for values.
Table 500-2: Mixing, Laying and Rolling Temperatures for Bituminous Mixes (°C)
Bitumen Viscosity Grade
Bitumen Temp (°C)
Aggregate Temp (°C)
Mixed Material Temp (°C)
Laying Temp (Min °C)
Rolling Temp (Min °C)
VG-40
160–170
160–175
160–170
150
100
VG-30
150–165
150–170
150–165
140
90
VG-20
145–165
145–170
145–165
135
85
VG-10
140–160
140–165
140–160
130
80
Note: Rolling must be completed before the mat cools below the minimum rolling temperature indicated above. The difference between binder and aggregate temperatures should not exceed 14°C.
Table 500-12 — Minimum Percent Voids in Mineral Aggregate (VMA)
Nominal Max Particle Size (mm)
Min VMA @ 3.0%
Min VMA @ 4.0%
Min VMA @ 5.0%
26.5
11.0
12.0
13.0
37.5
10.0
11.0
12.0
Interpolate VMA for intermediate air voids values. Example: if air voids = 3.5% between 3.0 and 4.0, interpolate linearly.
When the laying of the mixture is to be suspended long enough to permit the mixture to become chilled, a transverse joint shall be constructed.
All transverse joints shall be cut vertically to the full thickness of the previously laid mix using an asphalt cutter or pavement breaker, and the surface shall be painted with hot bitumen before placing fresh material.
The joint shall be constructed square to the lane alignment, and all excess materials shall be removed and cut back into the previously constructed pavement to the point of full pavement depth.
The exposed edge of the previously constructed pavement shall then be lightly coated with tack coat.
Longitudinal Joints
The paver used covers the required width, so typically there will be no longitudinal joints. However, if longitudinal joints are necessary, the edges shall be constructed true to the delineating line parallel to the center line of the road.
All joints shall be cut vertically to the full thickness of the previously laid mix and the surface painted with hot bitumen before placing fresh material.
Longitudinal joints shall preferably be hot joints. Cold longitudinal joints shall be properly heated with a joint heater to attain a suitable temperature before laying the adjacent material.
Surface Finish and Quality of Work
Final surface finish must meet MoRTH Clause 902 tolerances. Verify compaction, evenness and absence of segregation before acceptance.
Highway Construction Quality Control Tests | DBM & Bituminous Pavement
Highway Construction Quality Control Tests
A. Binder Tests
S. No.
Characteristic
Purpose
Test Method (IS Code/Standard)
Typical Requirement (VG30)
Test Frequency
i
Absolute Viscosity @ 60°C
Measures resistance to flow at high pavement temperatures
IS 1206 (Part 2)
2400 – 3600 Poises
Per lot / consignment
ii
Kinematic Viscosity @ 135°C
Ensures proper coating during mixing and compaction
DBM is a dense-graded bituminous mix used as a binder course in flexible pavements, placed below the Bituminous Concrete (BC) layer. It provides structural strength and distributes traffic loads to the lower layers.
2. What are the key materials used in DBM construction?
The main materials include crushed aggregates, filler, and VG-30 or VG-40 bitumen. Sometimes, modified bitumen (PMB/CRMB) is used for higher traffic conditions.
3. What is the typical thickness of DBM layers?
The DBM layer is generally laid in thicknesses of 50 mm to 100 mm, depending on the pavement design and traffic category.
4. What are the key quality control tests for DBM?
Major QC tests include: aggregate impact/abrasion value, flakiness index, binder content, mix grading, stability and flow, density, and temperature control during mixing and compaction (as per MoRTH 507).
5. What are the compaction requirements for DBM?
The target field density should not be less than 98% of the Marshall density. Proper rolling with tandem, pneumatic, and vibratory rollers is essential for achieving uniform compaction.
6. What is the minimum temperature requirement during DBM laying?
The mix temperature at the time of laying should be around 140–160°C, and compaction should begin before it drops below 120°C. Binder temperature should be checked at regular intervals.
7. What MoRTH clause governs DBM construction?
Dense Bituminous Macadam is governed by Clause 507 of MoRTH Specifications (5th Revision), covering materials, mix design, laying, compaction, and quality control requirements.
🛣️ Highway Construction Methodology Series
Explore step-by-step construction methods for all pavement layers as per MoRTH 5th Revision and IRC Guidelines.