Top 8 Proven Steps for Dense Bituminous Macadam (DBM) Construction Methodology — MoRTH Clause 507

Top 8 Proven Steps for Dense Bituminous Macadam (DBM) Construction Methodology — MoRTH Clause 507

Author: Kishor Kumar | Category: Bituminous Works | Updated: 2025

Quick Summary: Dense Bituminous Macadam (DBM) is a dense-graded hot mix used as a binder/base course. This article summarises the material requirements, mix design criteria, MoRTH Tables (500-9 to 500-13), and the Top 8 Proven Steps for execution and quality control as per MoRTH Clause 507.

Quick Reference — DBM (MoRTH 507)

  • Applicable Clause: MoRTH Clause 507 (DBM / Base / Binder Course)
  • Nominal Sizes: 37.5 mm (Grading 1) / 26.5 mm (Grading 2)
  • Compacted Thickness: 50–100 mm (single layer) or as per design
  • Bitumen: VG-30 / VG-40 or PMB as per Contract
  • Min. Binder Content: Table 500-10 (Min 4.0% for Grading 1; Min 4.5% for Grading 2)
  • Field Density: ≥ 98% Marshall density (or ≥92% Gmm as per contract)

Scope

This DBM construction methodology provides details of mandatory requirements for construction in single or multiple layers of Dense Bituminous Macadam (DBM) on a previously prepared Wet Mix Macadam base. The thickness of a single layer shall be between 50 mm to 100 mm or as per approved design and drawings.

Codal Provisions

  1. Contract Agreement
  2. IRC: SP: 84-2014
  3. MoRTH Specifications for Road & Bridge Works (5th Revision)
  4. Relevant Drawings

Plant & Equipment Required

Requirement of Materials

MaterialRequirement / Specification
BitumenVG-30 or VG-40 (or PMB as per CA / IS 73 / IS 15462). Grade as per contract / climatic requirements.
Coarse AggregatesCrushed rock / crushed gravel retained on 2.36 mm; clean, durable, cubical; satisfy LA abrasion/AIV, flakiness & elongation limits.
Fine AggregatesPassing 2.36 mm, retained on 75 µ; sand equivalent ≥ 50; PI ≤ 4.
FillerRock dust / hydrated lime / cement approved by AE; grading per Table 500-9.
Quality TestsIS:2386 (parts), IS:6241 (coating), AASHTO T283, IS:2720 series, Marshall stability (MS-2 / ASTM).

Note: Submit material source & test reports for AE approval prior to use.

Table 500-9: Grading Requirements for Mineral Filler

IS Sieve (mm)Cumulative % Passing
0.6100
0.395–100
0.07585–100

In bituminous mixes, filler refers to fine material (passing 0.075 mm sieve) added to fill the voids in the mineral aggregate and improve the stability, density, and binding of the mix.

Common Fillers Used in Bituminous Mixes

  1. Ordinary Portland Cement (OPC)
  2. Lime (Hydrated or Quicklime)
  3. Stone Dust / Crusher Dust
  4. Fly Ash
  5. Baghouse Dust
  6. Rock Dust / Mineral Filler

Specification Reference: As per MoRTH Clause 507.2.4 & IS: 73.

Table 500-10: Composition of Dense Graded Bituminous Macadam

Grading1 (Nominal 37.5 mm)2 (Nominal 26.5 mm)
Layer thickness (mm)75–10050–75
IS sieve 45 mm100100
IS sieve 37.5 mm95–100100
IS sieve 26.5 mm63–9390–100
IS sieve 19 mm-71–95
IS sieve 13.2 mm55–7556–80
IS sieve 4.75 mm38–5438–54
IS sieve 2.36 mm28–4228–42
IS sieve 0.3 mm7–217–21
IS sieve 0.075 mm2–82–8
Bitumen content (% by mass)Min 4.0*Min 4.5*

The bitumen content is based on aggregates with a specific gravity of 2.7. Adjust for aggregate specific gravity and climatic conditions as required by MoRTH.

Table 500-11: Requirements for Dense Graded DBM (Marshall / Modified Marshall)

PropertyModified Bitumen (Hot climate)Modified Bitumen (Cold climate)Test Method
Compaction Level75 blows on each face of specimen
Minimum Stability (kN)12.010.0AASHTO T245
Marshall Flow (mm)2.5–43.5–5AASHTO T245
Marshall Quotient2.5–5MS-2 / ASTM
% Air Voids3–5%3–5%
% VFB65–75%65–75%
Coating of Aggregate95% min — IS:6241
TSR≥80% — AASHTO T283

Comparison of Standard and Modified Marshall Methods

ParameterStandard Marshall TestModified Marshall Test (ASTM D5581 / MS-2)
Applicable Aggregate SizeUp to 26.5 mmUp to 38 mm (1.5 inch)
Specimen Diameter101.6 mm (4 inch)152.4 mm (6 inch)
Specimen Height63.5 ± 1.3 mm95.2 ± 1.3 mm
Hammer Weight4.5 kg10.2 kg (mechanical only)
No. of Blows per Face50 or 75 blows1.5× standard (75 or 112 blows)
Minimum Stability CriteriaAs per MoRTH Table 500-122.25 × standard value
Flow Value2–4 mm3–6 mm (1.5× range)

The Modified Marshall Method is adopted for bituminous mixes containing aggregates up to 38 mm nominal size (such as DBM Grading 1).

Table 500-13: Permissible JMF Variations

ParameterPermissible Variation
Aggregate passing 19 mm or larger±8%
Aggregate passing 13.2 / 9.5 mm±7%
Aggregate passing 4.75 mm±6%
Aggregate passing 2.36 / 1.18 / 0.6 mm±5%
Aggregate passing 0.3 / 0.15 mm±4%
Aggregate passing 0.075 mm±2%
Binder content±0.3%
Mixing temperature±10°C

MoRTH allows tolerances in production to ensure performance — see Table 500-13 for values.

Table 500-2: Mixing, Laying and Rolling Temperatures for Bituminous Mixes (°C)

Bitumen Viscosity GradeBitumen Temp (°C)Aggregate Temp (°C)Mixed Material Temp (°C)Laying Temp (Min °C)Rolling Temp (Min °C)
VG-40160–170160–175160–170150100
VG-30150–165150–170150–16514090
VG-20145–165145–170145–16513585
VG-10140–160140–165140–16013080

Note: Rolling must be completed before the mat cools below the minimum rolling temperature indicated above. The difference between binder and aggregate temperatures should not exceed 14°C.

Table 500-12 — Minimum Percent Voids in Mineral Aggregate (VMA)

Nominal Max Particle Size (mm)Min VMA @ 3.0%Min VMA @ 4.0%Min VMA @ 5.0%
26.511.012.013.0
37.510.011.012.0

Interpolate VMA for intermediate air voids values. Example: if air voids = 3.5% between 3.0 and 4.0, interpolate linearly.

Construction Operation — Top 8 Proven Steps

  1. Step 1 — Weather & Planning: Follow MoRTH Clause 501.5.1 for seasonal/weather limitations.
  2. Step 2 — Preparation of Base: Ensure underlying layer is prepared, prime/tack coat applied.
  3. Step 3 — JMF Approval & Plant Trials: Produce and submit Job Mix Formula (JMF) to AE and perform plant trials.
  4. Step 4 — Mixing & Temperatures: Mix in batch-type plant; maintain design temperatures ±10°C.
  5. Step 5 — Transportation & Laying: Transport mix in covered tippers; lay with sensor-controlled paver.
  6. Step 6 — Compaction: Begin compaction immediately using steel tandem rollers.
  7. Step 7 — Field Density & Quality Checks: Take cores/NDT; ensure minimum density ≥98% of Marshall.
  8. Step 8 — Surface Finish & Acceptance: Verify surface evenness, check for segregation, flush/tender spots.

Joints

Transverse Joints

When the laying of the mixture is to be suspended long enough to permit the mixture to become chilled, a transverse joint shall be constructed. All transverse joints shall be cut vertically to the full thickness of the previously laid mix using an asphalt cutter or pavement breaker, and the surface shall be painted with hot bitumen before placing fresh material.

The joint shall be constructed square to the lane alignment, and all excess materials shall be removed and cut back into the previously constructed pavement to the point of full pavement depth. The exposed edge of the previously constructed pavement shall then be lightly coated with tack coat.

Longitudinal Joints

The paver used covers the required width, so typically there will be no longitudinal joints. However, if longitudinal joints are necessary, the edges shall be constructed true to the delineating line parallel to the center line of the road. All joints shall be cut vertically to the full thickness of the previously laid mix and the surface painted with hot bitumen before placing fresh material.

Longitudinal joints shall preferably be hot joints. Cold longitudinal joints shall be properly heated with a joint heater to attain a suitable temperature before laying the adjacent material.

Surface Finish and Quality of Work

Final surface finish must meet MoRTH Clause 902 tolerances. Verify compaction, evenness and absence of segregation before acceptance.

Highway Construction Quality Control Tests | DBM & Bituminous Pavement

Highway Construction Quality Control Tests

A. Binder Tests

S. No.CharacteristicPurposeTest Method (IS Code/Standard)Typical Requirement (VG30)Test Frequency
iAbsolute Viscosity @ 60°CMeasures resistance to flow at high pavement temperaturesIS 1206 (Part 2)2400 – 3600 PoisesPer lot / consignment
iiKinematic Viscosity @ 135°CEnsures proper coating during mixing and compactionIS 1206 (Part 3)350 cSt (min.)Per lot / consignment
iiiPenetration @ 25°CMeasures hardness under standard loadIS 120345 mm (min.)Per lot / consignment
ivFlash Point (COC)Safe heating limit to prevent fireIS 1209220°C (min.)Per lot / consignment
vSolubility in TrichloroethyleneChecks purity of bitumenIS 121699.0% (min.)Per lot / consignment
viRTFO Residue TestsMeasures short-term aging resistanceIS 9382Viscosity Ratio ≤ 4; Ductility ≥ 40 cmPer lot / consignment
viiElastic RecoveryFatigue resistanceIS 1546250–75% (min.)Per lot / consignment
viiiSeparation TestStorage stability of modifierIS 15462, App. ASoftening Point difference ≤ 2.5°CPer lot / consignment
ixSoftening PointTemperature susceptibility & rutting resistanceIS 120550–75°C (depending on grade)Per lot / consignment

B. Aggregate Tests

S. No.TestPurposeMinimum Frequency
iiAggregate Impact Value / Los Angeles AbrasionAggregate strength1 test per 350 m³ per source or on quality change
iiiFlakiness & Elongation IndicesShape of aggregate1 test per 350 m³ per source or on quality change
ivSoundness (Na₂SO₄ / MgSO₄)Weathering resistance1 test per source or on quality change
vWater AbsorptionChecks porosity1 test per source or on quality change
viSand EquivalentFines content / cleanliness1 test per source or on quality change
viiPlasticity IndexSoil plasticity1 test per source or on quality change
viiiPolished Stone ValueSkid resistance1 test per source or on quality change
ix% Fractured FaceAggregate angularity1 test per 350 m³ when crushed gravel is used

C. Bituminous Mix Tests

S. No.TestPurposeMinimum Frequency
xMix GradingGradation of mix1 set per 400 t of mix, minimum 2/day/plant
xiStability & Voids AnalysisStrength, flow, density, void content3 tests per 400 t of mix, minimum 2/day/plant
xiiMoisture Susceptibility (MSHTO T283)Resistance to moisture damage1 test per mix type or on aggregate/source change
xivBinder ContentCorrect proportion in mix1 set per 400 t of mix, minimum 2/day/plant

D. Process Control & Field Tests

S. No.TestPurposeFrequency
xiiiTemperature (Binder, Aggregate, Mix)Ensure proper mixing and compactionAt regular intervals
xvRate of SpreadProper layer thickness in fieldAfter every 5th truck load
xviDensity of Compacted LayerEnsures compaction meets specification1 test per 700 m²

💡 Frequently Asked Questions – Dense Bituminous Macadam (DBM)

1. What is Dense Bituminous Macadam (DBM)?

DBM is a dense-graded bituminous mix used as a binder course in flexible pavements, placed below the Bituminous Concrete (BC) layer. It provides structural strength and distributes traffic loads to the lower layers.

2. What are the key materials used in DBM construction?

The main materials include crushed aggregates, filler, and VG-30 or VG-40 bitumen. Sometimes, modified bitumen (PMB/CRMB) is used for higher traffic conditions.

3. What is the typical thickness of DBM layers?

The DBM layer is generally laid in thicknesses of 50 mm to 100 mm, depending on the pavement design and traffic category.

4. What are the key quality control tests for DBM?

Major QC tests include: aggregate impact/abrasion value, flakiness index, binder content, mix grading, stability and flow, density, and temperature control during mixing and compaction (as per MoRTH 507).

5. What are the compaction requirements for DBM?

The target field density should not be less than 98% of the Marshall density. Proper rolling with tandem, pneumatic, and vibratory rollers is essential for achieving uniform compaction.

6. What is the minimum temperature requirement during DBM laying?

The mix temperature at the time of laying should be around 140–160°C, and compaction should begin before it drops below 120°C. Binder temperature should be checked at regular intervals.

7. What MoRTH clause governs DBM construction?

Dense Bituminous Macadam is governed by Clause 507 of MoRTH Specifications (5th Revision), covering materials, mix design, laying, compaction, and quality control requirements.

🛣️ Highway Construction Methodology Series

Explore step-by-step construction methods for all pavement layers as per MoRTH 5th Revision and IRC Guidelines.

← Previous: Methodology for Tack Coat Application Next: Methodology for BC Laying →

Related Posts: