Table of Contents
ToggleFrequently Asked Question
Ans: In field quality control of Wet Mix Macadam (WMM) layers, determining in-situ density is essential to ensure proper compaction and performance. Two standard methods are used: the sand replacement method and the core cutter method, as per IS: 2720 (Part 28 & Part 29) and MoRTH Section 900.
For WMM, which consists of coarse aggregates and fines bound by water, the sand replacement method is the more suitable and widely accepted approach. A small pit is excavated, the excavated material is weighed, and calibrated dry sand is poured into the hole to determine its volume. The field density is then computed and compared with the laboratory Modified Proctor density (IS: 2720 Part 8) to assess compaction efficiency (usually ≥98%).
The core cutter method, while simpler, is applicable mainly to fine-grained cohesive soils like subgrade or sub-base layers. It is not recommended for granular layers such as WMM because coarse particles cause inaccurate volume measurement and poor sample recovery.
Thus, for WMM verification, the sand replacement method remains the standard and most reliable procedure to validate compaction levels in line with MoRTH 5th Revision Clause 406 & 900.
Ans: The Optimum Moisture Content (OMC) for subgrade soil is the moisture level at which the soil attains maximum dry density (MDD) during compaction. Determining and maintaining this condition in the field is critical to achieve desired strength, stability, and load-bearing capacity of the pavement foundation.
In practice, OMC is first determined in the laboratory using the Standard or Modified Proctor Test (IS: 2720 Part 7 or Part 8). The dry density–moisture content curve obtained identifies the OMC corresponding to the peak dry density.
At site, field compaction is verified by:
·      Moisture control: The soil is adjusted near its OMC by adding or drying water and thoroughly mixing.
·      Trial compaction: A few test sections are compacted at different moisture levels (±1–2% of lab OMC) to observe density results and roller efficiency.
·      Field density checks: Using the sand replacement or nuclear density gauge methods, in-situ density is compared with MDD to ensure ≥97% (as per MoRTH).
Thus, the optimum moisture content in field is achieved by correlating lab OMC with actual site conditions, soil type, and roller performance to ensure maximum compaction and uniform subgrade strength.
Ans: The Acceptable Specification Limits of DBM is 27 and 24 for BC layers.
Ans. The acceptable specification limit of FSI – IS:2720 (Part-40) should not be greater than 50%.Â
Ans. The Los Angeles Abrasion (LAA) and Aggregate Impact Value (AIV) tests both evaluate the durability and toughness of aggregates, but they differ in loading type, purpose, and mechanism of degradation. Here are the key differences:
Aspect | Los Angeles Abrasion Test (LAA) | Aggregate Impact Value Test (AIV) |
Purpose | Measures resistance of aggregates to abrasion and attrition (wear due to friction). | Measures resistance of aggregates to sudden impact or shock loads. |
Test Standard | IS: 2386 (Part IV) – Abrasion test | IS: 2386 (Part IV) – Impact test |
Equipment Used | Los Angeles Abrasion machine with steel balls | Impact testing machine with a dropping hammer |
Type of Load Applied | Rotational impact and rubbing (abrasion) | Vertical impact (shock) |
Simulates Field Condition | Traffic wear and rolling of vehicle tyres | Sudden impact loads from moving traffic or compaction |
Nature of Breakdown | Gradual wearing and grinding of particles | Fracturing or breaking of aggregates |
Result Expressed As | % Los Angeles Abrasion Value (weight loss) | % Aggregate Impact Value (weight of fines) |
Acceptable Limits (MoRTH) | ≤ 35% for surface courses | ≤ 30% for surface courses |
Â
In summary:
LAA assesses wear resistance under abrasion, while AIV measures toughness under impact. Both tests complement each other in evaluating aggregate quality for road construction.
As per MoRTH Specifications, Section 900 (Table 900-3), the frequency of testing for Bituminous Mix (DBM/BC) is established to ensure consistent quality control during production and laying operations. The testing regime covers both constituent materials and finished mix properties at prescribed minimum frequencies.
For constituent materials, the following tests are specified:
Aggregate Impact Value / Los Angeles Abrasion Value – one test per 350 m³ of aggregate or whenever there is a change in source or quality.
Flakiness and Elongation Indices – one test per 350 m³ of aggregate.
Soundness (Sodium/Magnesium Sulphate) and Water Absorption – one test per source or when quality changes.
Sand Equivalent, Plasticity Index, and Polished Stone Value – one test per source or change in aggregate quality.
For the bituminous mix, the key tests and frequencies are:
Mix grading – one set per 400 tonnes of mix, with a minimum of two tests per day per plant.
Stability and Voids analysis (Marshall test) – three tests for each 400 tonnes of mix, minimum two sets per day.
Moisture susceptibility (AASHTO T283) – one test per mix type or when material source changes.
Binder content – one test per 400 tonnes, minimum two per day per plant.
Temperature control (binder, aggregate, mix) – checked at regular intervals.
Rate of spread – verified every 5th truckload.
Field density of compacted layer – one test per 700 m² area.
Ans: In field quality control of Wet Mix Macadam (WMM) layers, determining in-situ density is essential to ensure proper compaction and performance. Two standard methods are used: the sand replacement method and the core cutter method, as per IS: 2720 (Part 28 & Part 29) and MoRTH Section 900.
For WMM, which consists of coarse aggregates and fines bound by water, the sand replacement method is the more suitable and widely accepted approach. A small pit is excavated, the excavated material is weighed, and calibrated dry sand is poured into the hole to determine its volume. The field density is then computed and compared with the laboratory Modified Proctor density (IS: 2720 Part 8) to assess compaction efficiency (usually ≥98%).
The core cutter method, while simpler, is applicable mainly to fine-grained cohesive soils like subgrade or sub-base layers. It is not recommended for granular layers such as WMM because coarse particles cause inaccurate volume measurement and poor sample recovery.
Â
Thus, for WMM verification, the sand replacement method remains the standard and most reliable procedure to validate compaction levels in line with MoRTH 5th Revision Clause 406 & 900.
Ans: The Optimum Moisture Content (OMC) for subgrade soil is the moisture level at which the soil attains maximum dry density (MDD) during compaction. Determining and maintaining this condition in the field is critical to achieve desired strength, stability, and load-bearing capacity of the pavement foundation.
In practice, OMC is first determined in the laboratory using the Standard or Modified Proctor Test (IS: 2720 Part 7 or Part 8). The dry density–moisture content curve obtained identifies the OMC corresponding to the peak dry density.
At site, field compaction is verified by:
·      Moisture control: The soil is adjusted near its OMC by adding or drying water and thoroughly mixing.
·      Trial compaction: A few test sections are compacted at different moisture levels (±1–2% of lab OMC) to observe density results and roller efficiency.
·      Field density checks: Using the sand replacement or nuclear density gauge methods, in-situ density is compared with MDD to ensure ≥97% (as per MoRTH).
Â
Thus, the optimum moisture content in field is achieved by correlating lab OMC with actual site conditions, soil type, and roller performance to ensure maximum compaction and uniform subgrade strength.
Ans: The Acceptable Specification Limits of DBM is 27 and 24 for BC layers.
Ans. The acceptable specification limit of FSI – IS:2720 (Part-40) should not be greater than 50%.Â
Ans. The Los Angeles Abrasion (LAA) and Aggregate Impact Value (AIV) tests both evaluate the durability and toughness of aggregates, but they differ in loading type, purpose, and mechanism of degradation. Here are the key differences:
Aspect | Los Angeles Abrasion Test (LAA) | Aggregate Impact Value Test (AIV) |
Purpose | Measures resistance of aggregates to abrasion and attrition (wear due to friction). | Measures resistance of aggregates to sudden impact or shock loads. |
Test Standard | IS: 2386 (Part IV) – Abrasion test | IS: 2386 (Part IV) – Impact test |
Equipment Used | Los Angeles Abrasion machine with steel balls | Impact testing machine with a dropping hammer |
Type of Load Applied | Rotational impact and rubbing (abrasion) | Vertical impact (shock) |
Simulates Field Condition | Traffic wear and rolling of vehicle tyres | Sudden impact loads from moving traffic or compaction |
Nature of Breakdown | Gradual wearing and grinding of particles | Fracturing or breaking of aggregates |
Result Expressed As | % Los Angeles Abrasion Value (weight loss) | % Aggregate Impact Value (weight of fines) |
Acceptable Limits (MoRTH) | ≤ 35% for surface courses | ≤ 30% for surface courses |
In summary:
LAA assesses wear resistance under abrasion, while AIV measures toughness under impact. Both tests complement each other in evaluating aggregate quality for road construction.
As per MoRTH Specifications, Section 900 (Table 900-3), the frequency of testing for Bituminous Mix (DBM/BC) is established to ensure consistent quality control during production and laying operations. The testing regime covers both constituent materials and finished mix properties at prescribed minimum frequencies.
For constituent materials, the following tests are specified:
Aggregate Impact Value / Los Angeles Abrasion Value – one test per 350 m³ of aggregate or whenever there is a change in source or quality.
Flakiness and Elongation Indices – one test per 350 m³ of aggregate.
Soundness (Sodium/Magnesium Sulphate) and Water Absorption – one test per source or when quality changes.
Sand Equivalent, Plasticity Index, and Polished Stone Value – one test per source or change in aggregate quality.
For the bituminous mix, the key tests and frequencies are:
Mix grading – one set per 400 tonnes of mix, with a minimum of two tests per day per plant.
Stability and Voids analysis (Marshall test) – three tests for each 400 tonnes of mix, minimum two sets per day.
Moisture susceptibility (AASHTO T283) – one test per mix type or when material source changes.
Binder content – one test per 400 tonnes, minimum two per day per plant.
Temperature control (binder, aggregate, mix) – checked at regular intervals.
Rate of spread – verified every 5th truckload.
Field density of compacted layer – one test per 700 m² area.
Earthwork Methodology – FAQs
-
What is earthwork in highway construction?
Earthwork involves excavation, embankment formation, filling, and compaction of soil to achieve required formation levels as per approved drawings.
-
Which MoRTH clause governs earthwork?
Earthwork is governed under MoRTH Section 300, mainly Clauses 301 to 305.
-
What is the required compaction for embankment?
Embankment layers must be compacted to minimum 95% MDD, while subgrade requires 97% MDD.
-
What is OMC in earthwork?
OMC (Optimum Moisture Content) is the moisture level at which maximum dry density is achieved during compaction.
-
How is field density tested?
Field density is tested using Sand Replacement or Core Cutter methods as per IS 2720.
-
What is the maximum layer thickness?
Loose thickness of earthwork layers should generally not exceed 200 mm.
-
What soil tests are mandatory?
CBR, LL, PL, PI, grain size analysis, and Proctor compaction tests.
-
Why is proper drainage important?
Poor drainage weakens subgrade and leads to rutting and settlement.
-
Can unsuitable soil be used?
Unsuitable soils like organic or highly plastic soils are not permitted.
-
What happens if compaction fails?
The layer must be reworked, moisture adjusted, and recompacted.
Frequently Asked Questions (FAQ) – Fly Ash Embankment
-
What is a fly ash embankment?
A fly ash embankment is constructed by replacing part of natural soil with fly ash, a by-product of thermal power plants, to build cost-effective, lightweight, and environmentally friendly road embankments.
-
Which MoRTH clause covers fly ash embankments?
Fly ash embankments are referenced in MoRTH Clause 305 and relevant IRC guidelines for stabilized fly ash usage.
-
What type of fly ash is used?
Class F or Class C fly ash from thermal power plants, free from unburnt carbon and meeting IS 3812 Part 1 specifications, is used.
-
Why use fly ash in embankments?
Fly ash reduces embankment weight, improves workability, enhances long-term stability, and promotes sustainable construction by reusing industrial by-products.
-
How is fly ash compacted?
Fly ash is laid in layers (150–250 mm), lightly moistened, and compacted using vibratory rollers to achieve the specified dry density.
-
What is the optimum moisture content (OMC)?
OMC is determined by the Modified Proctor Test to achieve maximum dry density and stability for the fly ash embankment.
-
What tests are required for quality control?
Key tests include dry density, moisture content, CBR, unconfined compressive strength, and settlement monitoring.
-
What layer thickness is recommended?
Compacted layer thickness typically ranges from 150 mm to 250 mm per lift, depending on embankment height and material stability.
-
What are the benefits of fly ash embankments?
Benefits include reduced construction cost, lower settlement, improved sustainability, and efficient utilization of industrial waste.
-
Can fly ash embankments be used in all soil types?
They are best suited for low-plasticity soils; high-plasticity clays may require blending or stabilization with lime/cement for adequate performance.
Frequently Asked Questions (FAQ) – Subgrade
-
What is subgrade in highway construction?
Subgrade is the topmost layer of the earthwork, providing a stable foundation for all subsequent pavement layers such as GSB, WMM, and bituminous courses.
-
Which MoRTH clause covers subgrade?
Subgrade construction is specified under MoRTH Clause 301–303, including soil preparation, compaction, and drainage requirements.
-
What materials are used for subgrade?
Subgrade is typically formed with existing soil, earth, or selected borrow material meeting MoRTH gradation, plasticity, and CBR requirements.
-
What is the purpose of proper subgrade preparation?
Proper preparation ensures uniform support, prevents differential settlement, provides adequate drainage, and prolongs pavement life.
-
What is the required compaction for subgrade?
Each subgrade layer should be compacted to at least 97% of Maximum Dry Density (MDD) as per Modified Proctor Test (IS 2720 Part 8).
-
How thick should subgrade layers be?
Compacted layer thickness is usually 150–250 mm per lift, with multiple lifts used for high embankments or weak soils.
-
What quality control tests are required?
Tests include dry density, moisture content, CBR, Atterberg limits, and field level checks to ensure compliance with design specifications.
-
How is subgrade drainage ensured?
Proper side slopes, cross-fall, and subsoil drains prevent water accumulation, maintaining subgrade strength and minimizing settlement.
-
What are common defects in subgrade?
Defects include soft spots, uneven compaction, rutting, poor drainage, and excessive settlement, all of which affect pavement performance.
-
Can weak soils be improved for subgrade?
Yes, weak soils can be stabilized using lime, cement, fly ash, or geosynthetics to meet the required strength and CBR for subgrade construction.
Frequently Asked Questions (FAQ) – Cement Treated Granular Sub-Base (CTGSB)
-
What is CTGSB in highway construction?
CTGSB is a stabilized base layer created by mixing well-graded granular aggregates with cement, providing high strength, reduced permeability, and improved load-bearing capacity for pavement structures.
-
Which MoRTH clause covers CTGSB?
CTGSB construction is specified under MoRTH Clause 504 for cement-treated base layers.
-
What type of cement is used in CTGSB?
Ordinary Portland Cement (OPC) of 43 or 53 grade, conforming to IS:269, is commonly used.
-
Why use cement in granular sub-base?
Cement acts as a stabilizer, increasing strength, stiffness, and durability, while reducing susceptibility to moisture and deformation under traffic.
-
What is the typical cement content for CTGSB?
Cement content typically ranges from 3% to 6% by weight of dry aggregates, depending on material properties and design requirements.
-
How is CTGSB compacted?
The mixture is laid in layers of 150–200 mm, watered to optimum moisture content, and compacted using vibratory or pneumatic rollers to achieve target density.
-
What tests are performed for CTGSB quality control?
Tests include dry density, moisture content, unconfined compressive strength (UCS), CBR, and thickness verification.
-
What is the curing period for CTGSB?
After compaction, the layer should be cured for at least 7 days by sprinkling water to achieve desired strength and prevent cracking.
-
What thickness is recommended for CTGSB layers?
Compacted thickness typically ranges from 150–250 mm per layer, based on pavement design and traffic loading.
-
What are common defects in poorly executed CTGSB?
Poor cement dispersion, insufficient compaction, or inadequate curing can cause cracking, settlement, reduced strength, and premature pavement failure.
Frequently Asked Questions (FAQ) – Granular Sub-Base (GSB)
-
What is Granular Sub-Base (GSB)?
Granular Sub-Base (GSB) is a layer of well-graded granular material placed above the prepared subgrade to distribute traffic loads, improve drainage, and provide a stable working platform for upper pavement layers.
-
Which MoRTH clause governs GSB construction?
GSB construction is governed under MoRTH Clause 401 of Section 400, which specifies material grading, construction procedure, compaction, and tolerances.
-
What materials are permitted for GSB?
Materials such as crushed stone, gravel, sand, moorum, slag, or a combination thereof are permitted, provided they are clean, hard, durable, and free from organic or deleterious matter.
-
What is the required compaction for GSB?
GSB layers must be compacted to at least 98% of Maximum Dry Density (MDD) determined by the Modified Proctor Test.
-
What is the maximum thickness of a GSB layer?
The compacted thickness of a single GSB layer should generally not exceed 150 mm. Thicker sections must be laid and compacted in multiple layers.
-
Why is grading control important in GSB?
Proper grading ensures adequate load distribution, interlocking of particles, permeability for drainage, and prevention of segregation during laying and compaction.
-
What quality tests are performed on GSB materials?
Common tests include gradation analysis, Atterberg limits, Los Angeles Abrasion, Aggregate Impact Value, and field density tests.
-
How is field density of GSB checked?
Field density is generally checked using the Sand Replacement Method as per IS 2720 (Part 28) to verify the achieved compaction.
-
What are the surface tolerance limits for GSB?
Surface level tolerances for GSB are generally within ±20 mm longitudinally and ±15 mm transversely, as specified by MoRTH.
-
Can recycled or marginal materials be used in GSB?
Recycled or marginal materials may be used only with prior approval of the Authorized Engineer and if they fully comply with MoRTH grading and quality requirements.
Frequently Asked Questions (FAQ) – Wet Mix Macadam (WMM)
-
What is Wet Mix Macadam (WMM)?
Wet Mix Macadam (WMM) is a dense, mechanically mixed granular layer laid using crushed aggregates and water at optimum moisture content, providing a strong base for bituminous pavement layers.
-
Which MoRTH clause governs WMM construction?
WMM construction is governed under MoRTH Clause 406 of Section 400, covering materials, gradation, mixing, laying, and compaction requirements.
-
What materials are used in WMM?
WMM uses crushed stone aggregates with specified grading, mixed with water at controlled moisture content in a pug mill or WMM plant.
-
What is the compaction requirement for WMM?
WMM layers must be compacted to at least 98% of Maximum Dry Density (MDD) determined by the Modified Proctor Test.
-
What is the maximum thickness of a WMM layer?
The compacted thickness of a single WMM layer should generally not exceed 200 mm. Thicker layers must be constructed in multiple lifts.
-
Why is plant mixing mandatory for WMM?
Plant mixing ensures uniform distribution of aggregates and water, better control of gradation and moisture content, and consistent quality of the WMM layer.
-
What rollers are used for WMM compaction?
Compaction is typically carried out using vibratory rollers followed by smooth wheel rollers to achieve required density and surface finish.
-
How is field density of WMM checked?
Field density is checked using the Sand Replacement Method as per IS 2720 (Part 28) after final compaction.
-
What surface tolerance is allowed for WMM?
Surface tolerances are generally limited to ±10 mm in both longitudinal and transverse directions, as specified by MoRTH.
-
What happens if WMM fails density or grading tests?
The affected portion must be scarified, moisture-corrected, and recompacted or replaced until it meets MoRTH requirements.
Frequently Asked Questions (FAQ) – Prime Coat
-
What is a prime coat in road construction?
A prime coat is a low-viscosity bituminous liquid applied on a granular base to bind loose aggregates, seal the surface, and provide a bond for the subsequent bituminous layer.
-
Which MoRTH clause covers prime coat?
Prime coat is covered under MoRTH Clause 507 of Section 500.
-
What materials are used for prime coat?
Prime coat uses low-viscosity bitumen such as and sometimes cutback bitumen diluted with kerosene or diesel as per MoRTH specifications.
-
Why is prime coat applied?
It binds loose granular aggregates, reduces dust, seals voids, and improves adhesion for subsequent bituminous layers.
-
What is the typical application rate?
Prime coat is generally applied at 0.8–1.2 L/m², depending on surface texture and porosity of the base.
-
How should the surface be before applying prime coat?
The surface must be clean, dry, free from loose dust or debris, and uniformly graded.
-
What equipment is used for prime coat?
Prime coat is applied using bitumen sprayers or mechanical distributors to ensure uniform coverage.
-
How long should the prime coat cure before laying the next layer?
Typically, it should cure for 12–24 hours or until the bitumen is tack-free and the surface is dry enough to prevent slippage.
-
What defects can occur if prime coat is poorly applied?
Uneven application, puddling, or insufficient curing can cause poor adhesion, bleeding, or slippage of the bituminous layer.
-
Can prime coat be applied in wet conditions?
No, prime coat should be applied only on a dry, clean surface to ensure proper penetration and adhesion.
Frequently Asked Questions (FAQ) – Tack Coat
-
What is a tack coat in road construction?
Tack coat is a light application of bituminous binder applied between two bituminous layers to ensure proper adhesion and prevent slippage or delamination.
-
Which MoRTH clause covers tack coat?
Tack coat is specified under MoRTH Clause 508 in Section 500.
-
What type of bitumen is used for tack coat?
Cutback bitumen (e.g., SC-70) or emulsion bitumen (RS or CRS) is typically used, depending on temperature and project requirements.
-
What is the purpose of tack coat?
Tack coat provides a strong adhesive bond between old and new bituminous layers, preventing slippage, reflective cracking, and layer separation.
-
What is the recommended application rate?
The typical application rate is 0.3–0.5 L/m² for dense bituminous surfaces, and may vary depending on surface texture and porosity.
-
How should the existing surface be prepared before tack coat?
The surface must be clean, dry, free of dust, loose aggregates, and water to ensure proper bonding with the new layer.
-
What equipment is used to apply tack coat?
Tack coat is applied using a mechanical bitumen sprayer for uniform and controlled coverage across the surface.
-
How long should tack coat cure before laying the next layer?
It should cure until the surface becomes tacky but not wet, usually 30–60 minutes, depending on weather and bitumen type.
-
What defects can occur if tack coat is poorly applied?
Poor application may cause delamination, slippage, poor adhesion, and early pavement failure.
-
Can tack coat be applied in wet conditions?
No, the existing surface must be dry to ensure proper bonding; applying on wet surfaces reduces adhesion and leads to slippage.
Frequently Asked Questions (FAQ) – Dense Bituminous Macadam (DBM)
-
What is Dense Bituminous Macadam (DBM)?
Dense Bituminous Macadam (DBM) is a high-strength bituminous base course consisting of well-graded aggregates, bitumen binder, and filler, designed to withstand heavy traffic loads.
-
Which MoRTH clause governs DBM construction?
DBM construction is governed by MoRTH Clause 505 under Section 500, which specifies mix design, production, laying, compaction, and quality control.
-
Why is mix design important for DBM?
A proper mix design ensures optimum bitumen content, adequate stability, durability, and resistance to rutting and fatigue under traffic loads.
-
What type of bitumen is used in DBM?
Penetration grade bitumen such as VG-30 or VG-40 is commonly used, depending on climatic conditions and traffic intensity.
-
What is the thickness requirement for DBM?
DBM is typically laid in layers of 50–100 mm compacted thickness. Thicker layers are constructed in multiple lifts as per design.
-
What temperature control is required during DBM laying?
The mix should be laid and compacted within the specified temperature range to ensure proper workability, compaction, and bonding between layers.
-
What equipment is used for DBM construction?
DBM is laid using a sensor paver and compacted using a combination of vibratory, pneumatic-tyred, and tandem rollers.
-
What quality control tests are required for DBM?
Quality control tests include Marshall stability and flow, bitumen content, grading, core density, and surface regularity.
-
Why is proper compaction critical for DBM?
Proper compaction minimizes air voids, improves load distribution, and enhances durability and resistance to moisture damage.
-
What defects can occur if DBM is poorly executed?
Poor execution can result in rutting, cracking, ravelling, inadequate bonding, and reduced pavement life.
Frequently Asked Questions (FAQ) – DBM Profile Corrective Course
-
What is DBM Profile Corrective Course?
DBM Profile Corrective Course is a Dense Bituminous Macadam layer applied to correct surface irregularities, improve ride quality, and provide a uniform profile before the final wearing course.
-
Which MoRTH clause governs the Profile Corrective Course?
Profile corrective DBM is covered under MoRTH Clause 505 for intermediate and base bituminous layers.
-
Why is a Profile Corrective Course applied?
It corrects surface undulations, ruts, and unevenness from underlying layers, ensuring proper drainage and a smooth base for the final wearing course.
-
What is the typical layer thickness?
Thickness usually ranges from 25 mm to 50 mm compacted, depending on the amount of profile correction required.
-
What mix is used for DBM Profile Corrective Course?
Well-graded aggregates, mineral filler, and bitumen are mixed as per approved MoRTH DBM gradation and binder content.
-
What is the importance of compaction?
Proper compaction ensures uniform density, eliminates segregation, and provides structural strength for the final wearing course.
-
What equipment is used for laying and compaction?
A sensor-controlled paver lays the mix, followed by vibratory or pneumatic rollers for compaction to achieve specified density and smoothness.
-
What tests are conducted for DBM Profile Corrective Course?
Gradation, bitumen content, Marshall stability & flow, density, thickness, and surface smoothness tests are conducted as per MoRTH specifications.
-
How does it improve pavement performance?
By correcting the profile, it ensures uniform load distribution, reduces rutting, improves skid resistance, and enhances riding comfort.
-
Can multiple corrective layers be applied?
Yes, if the surface irregularities are significant, multiple thin DBM corrective layers can be applied, each compacted to specification before the next.
Frequently Asked Questions (FAQ) – Bituminous Concrete (BC)
-
What is Bituminous Concrete (BC)?
Bituminous Concrete (BC) is a dense, hot-laid bituminous mixture composed of well-graded aggregates, filler, and bitumen binder, forming the final surface layer of flexible pavements.
-
Which MoRTH clause governs BC construction?
BC construction is governed under MoRTH Clause 509 in Section 500, covering mix design, production, laying, compaction, and quality checks.
-
Why is mix design critical for BC?
Mix design ensures the right proportion of aggregates, filler, and bitumen to provide stability, durability, skid resistance, and resistance to rutting.
-
What bitumen grades are used in BC?
Penetration grade bitumen (VG-30 or VG-40) or modified bitumen may be used depending on climate, traffic, and design specifications.
-
What is the typical compacted thickness of BC?
BC layers are usually laid in 25–50 mm compacted thickness, depending on traffic intensity and design.
-
What temperature is required for BC laying?
BC must be laid at the optimum mixing and paving temperatures to ensure proper compaction and bonding with underlying layers.
-
What equipment is used for BC laying?
BC is laid using a sensor-controlled paver and compacted with vibratory and pneumatic rollers to achieve smoothness and density.
-
Which quality control tests are performed on BC?
Tests include gradation, bitumen content, Marshall stability and flow, density, voids analysis, and surface regularity.
-
Why is compaction critical in BC?
Proper compaction reduces air voids, improves load transfer, enhances skid resistance, and prevents premature rutting and bleeding.
-
What defects can occur if BC is poorly laid?
Poor laying can lead to segregation, bleeding, cracking, rutting, and reduced pavement life.
Frequently Asked Questions (FAQ) – Bituminous Concrete (BC) with Plastic Waste
-
What is BC with plastic waste?
BC with plastic waste is a bituminous concrete layer in which shredded waste plastics are mixed with bitumen to improve strength, flexibility, and sustainability while recycling plastic waste.
-
Which MoRTH clause covers plastic-modified BC?
Plastic-modified BC is referenced under MoRTH Clause 507 for environmental and performance considerations of bituminous layers.
-
What types of plastic can be used?
Commonly used plastics include polyethylene (PE), polypropylene (PP), and polystyrene (PS) in shredded or granulated form, free from contaminants.
-
Why add plastic to bituminous concrete?
Plastic improves the binder’s viscosity, enhances resistance to rutting and cracking, increases durability, and promotes sustainable waste management.
-
What is the typical plastic content?
Plastic content is typically 5–10% by weight of bitumen, depending on project specifications and aggregate type.
-
How is BC with plastic waste prepared?
Shredded plastic is melted and blended with hot bitumen, then mixed with heated aggregates in a hot mix plant, and finally laid and compacted on site.
-
What are the compaction requirements?
Compaction is similar to conventional BC using vibratory or pneumatic rollers to achieve specified density and void content as per MoRTH.
-
What tests are performed for quality control?
Tests include Marshall Stability, flow, bitumen content, aggregate gradation, density, voids, and rutting resistance.
-
What are the environmental benefits?
Recycling waste plastics reduces landfill usage, lowers carbon footprint, and conserves natural bitumen resources.
-
Can BC with plastic waste be used in all traffic conditions?
Yes, with proper mix design, it can be used for low, medium, and high traffic roads, offering improved rutting resistance and durability.
